GO Bond

In 2022, Las Cruces voters approved the issuance of $23 million in General Obligation bonds for projects that include the establishment of an affordable housing trust fund, the building of a new fire station on the east mesa, park improvements, and continued improvements of the East Mesa Recreation Complex.

Affordable Housing – Approved

Making it Accessible. Keeping it Affordable.

Housing Investment Strategy

The City of Las Cruces Affordable Housing Investment Strategy was adopted by the City Council on March 4th, 2024. The investment strategy outlines a deliberate allocation of the $6 million and aligns with the GO Bond timeline, spanning three years while remaining adaptable to market fluctuations and broader economic conditions. While this amount represents a substantial commitment, the City aims to maximize its impact. Gap funding will complement other sources of state and federal funding. Approximately 800 housing units are planned over the next three years, providing a much-needed boost to the affordable housing stock.

2024-2027 Affordable Housing Investment Strategy

Three Sisters Apartments – About 88% Complete as of April 28, 2025

The Three Sisters Apartments, a 70-unit complex (see graphic rendering image above for reference), is currently under construction. It consists of 30 one-bedroom units, 20 two-bedroom units, 19 three-bedroom units, and 1 manager’s unit. The apartment complex will be located at the intersection of Griggs and Walnut. The apartments will offer a range of amenities for residents, including a community room with a lounge, a community kitchen, and outdoor recreation spaces.

Update: 4/28/25
Some residents are already living in a few of the buildings.
Ribbon Cutting planned around Mid-May

Pedrena -About 74% Complete as of April 28, 2025

The Pedrena Senior Apartments comprise an 80-unit affordable housing complex situated on the corner of El Paseo and Farney Lane. Within the complex, there are 44 one-bedroom, one-bath units and 36 two-bedroom, two-bath units. Amenities at Pedrena Senior Apartments will include a library, a community kitchen, and covered gathering spaces.

Update 4/28/25: Exterior is near completion. Waiting for elevators to phase occupancy. Dog park is finalized and stucco is complete.

Peachtree Canyon – About 26% Complete as of April 28, 2025

The Peachtree Canyon Apartments are located on the corner of Jornada Road and Peachtree Hills. The first phase of the apartments will include 72 one-bedroom, 60 two-bedroom, and 12 three-bedroom units. Among the features offered by the apartment complex are pickleball courts, a pool, age-appropriate playgrounds, and a community building. Additionally, the apartments will operate entirely on electricity.

Update 4/28/25: Currently being framed. First residential building should be complete in September 2026, pre-leasing in August.

 

Golden colored shovels lined up in dirt for ceremonial groundbreakingThank you if you attended the groundbreaking ceremony of the Peachtree Canyon Apartments, a 144-unit affordable housing development on October 10, 2024.

This exciting project is being made possible through a partnership between the New Mexico Housing & Community Development CorporationThomas Development Group, the City of Las CrucesHousing New Mexico/MFA, and Doña Ana County.

 

 

Arcadia – Phase 4 (Subdivision Acquiring with GO Bonds to work on single family homes)

Update: 4/28/2025
Contract is out with Property seller.
Will Follow up with Council for approval.

Amador Crossing 

Amador Crossing is a 50-unit permanent supportive housing (PSH) complex comprising a mix of single room occupancy and one-bedroom units. The complex will accommodate a diverse population, including chronically homeless residents and voucher holders. Located at 1101 W. Amador, Amador Crossing is within the Mesilla Valley Community of Hope Campus (MVCH). This strategic placement within the MVCH campus ensures easy access for residents to the campus’s other five agencies, offering supportive services such as case management, food distribution, and a healthcare clinic.

Amador Crossing aims to create an inviting and comforting environment for the unhoused and at-risk community. It will provide a safe space for residents to heal, stabilize, and grow. The apartments are currently under the preliminary planning and design stage.

Update: The construction documents for Amador Crossing have been completed, and the request for bids will be published in October 2024. Construction is scheduled to begin in January 2025.

Citywide Benefits to Affordable/Attainable Housing

Citywide, there are many benefits to having affordable and attainable housing. First, it allows for people of all ages and income levels to live in the city. This is important because it ensures that everyone has access to the same opportunities and resources that the city has to offer. Additionally, having a variety of housing options helps to strengthen the economy by providing homes for people of all stages of life. This attracts new residents and businesses to the city, which in turn helps to create jobs and grow the local economy. Affordable and attainable housing is also beneficial for seniors who want to stay in their community as they age. It allows them to maintain their independence and stay connected to their friends and neighbors. Ultimately, having affordable and attainable housing throughout the city is essential for creating a thriving community for all residents.

New Fire Station – Approved

Enhance Public Safety & Shorten Response Time

The new fire station will help to ensure public safety by reducing response times for emergencies.

Fire Station 9 aerial view in Fall 2025 while being built. Apparatus bay at station 9 as it is being built.Fire Station 9 will reduce response times for the Sonoma Ranch and Central service area. Currently, the furthest area in a potential District 9 is 11:19 with light and sirens. All other areas in the City Fire averages 8:27. With Fire Station 9 in place, the response time for the furthest area in a potential District 9 will be reduced to 3-6 minutes. This will improve public safety for all residents in the service area.

Fire Station 9 will provide extra resources to the entire Highway 70 corridor.

Having an additional fire station on Sonoma Ranch would mean that there would be less of a need for other fire crews to respond from further away, which would reduce the amount of damage to property and injury to people in medical need. Additionally, it would mean less wear and tear on other apparatus that would be responding from further away.

Construction on the new Fire Station 9 in Las Cruces is ongoing. Completion is expected near the end of February 2026.

Communications Director Mandy Leatherwood (formerly Guss) spoke with Former Fire Chief Jason Smith about the new station in a segment of Ask The. Watch the Ask The Video below.

 

Park Improvements – Approved

Park Improvements Make Our City Better

The Parks GO Bond would mean basic improvements throughout the CIty’s parks.

The following images show portions of the park that will need upgrades including a bathroom, cracked sidewalks, playground equipment and benches.

These improvements would include safety, lighting, and shade enhancements at La Llorona Park.
(Parks previously considered for improvements other than La Llorona have been put on a wait list for additional future funding if available).

  • La Llorona Park
    • Restroom
    • Upgrade amenities
    • Trail repair
    • Replace Play equipment including safety surfacing
    • Wayfinding
    • Mitigate stormwater at playground
  • Other parks – Scope currently removed from GO-Bond.

Finally, the money would be used to add shade structures on the playscapes and bollards for safety and lighting. These enhancements will make our City’s parks even more enjoyable places to spend time with family and friends.

Parks are an essential part of our community.

Parks promote health and wellness. They drive programming and educational activities that impact childhood development. Parks create economic opportunity by attracting visitors and businesses. They unite people and strengthen communities by providing a common space for people to come together.

 

East Mesa Public Recreation Complex – Approved

Providing Needed Improvements to Where We’re Growing

The GO Bond would provide continued improvements for residents on the city’s growing east side.

The East Mesa Public Recreation Complex is a much-needed addition to the City’s park system, and the GO Bonds will help fund additional improvements to the facility. The initial phase of the project, including the installation of sport lighting, is expected to be completed in February or March of next year. This will allow for evening activities at the complex, which is great news for residents on the City’s growing east side.

Two basketball courts are slated to be constructed, and a restroom is planned. Street furniture will be installed, MUSCO lighting in being installed and there will be a 10×10 public art space.

The East Mesa Public Recreation Complex is a sister facility to the Hadley Sports Complex, and it will provide space for tournaments and league games. Additionally, the complex will have security lighting, which will help keep residents safe during evening events.

The East Mesa Public Recreation Complex is the City’s third community-sized park. Along with Young Park and Apodaca Park, this new facility will provide space for community events and family gatherings.

Allocating Bond Funding to Art – Approved

A Portion of Approved Bond Capacity Used for Public Art

The GO Bond would provide continued improvements for residents on the city’s growing east side.

Per Ordinance No. 2988 (Las Cruces Municipal Code (LCMC), 1997, Chapter 2, Administration, Article V, Finance, Division 4, Two Percent For Public Art), two percent of each GO Bond purpose shall be provided for Public Art.

Two percent of the entire GO Bond capacity approved by voters, regardless of the amount, will be allocated to public art which is used for the same bond purpose. The table below shows the two percent applied to the $23 million GO Bond capacity.

Department/Division*Allocated2% of each Bond Purpose for Public Art
Total Bond Program Funding$23,000,000
Bond Purpose
Affordable Housing$6,000,000N/A
Fire Station$10,000,000$200,000*
Park Improvements$2,000,000$40,000*
East Mesa Recreation Complex Phase 2$5,000,000$100,000*
Total Bond Capacity$23,000,000$340,000*

* These numbers are gross figures. Two percent funding will be calculated on the total net proceeds, after payment of costs of issuance to each project, per the ordinance.

Updates:

  • Fire Station #9 – Draft of the project plan based on stakeholder meetings is almost complete. Tentative date for presenting the plan to the City Art Board is February 8.
  • A second public art project is possible with funding received. Fire station site TBD.
  • Fire Station #9 – City Council approved the concept design recommended by the City Art Board at the September 3, 2024 council meeting.
  • Artist is in first phase of finalizing design, acquiring materials, to begin fabricating.
  • Go Bond funding is also being appropriated for two commissions at Fire Station 1 and Fire Station 6.

EMPRC –

  • Art project is on track to be installed by March 2026.
  • Cement pads were poured in December 2025 in preparation of the installation of the artwork.
  • Location has been chosen. Artist will begin fabricating his art piece in his studio.
  • Site visit by City Art Board members is scheduled for late January, early February to determine location of public art installation.
  • Project plan in progress based on stakeholder meetings.
  • Project design concept recommendation by the City Art Board was approved by City Council at the Oct. 7, 2024 council meeting.
  • Artist is in first phase of final design before beginning fabrication.

Park Improvements –

  • Artwork was installed by Kayla Blundell in November 2025. The steel metal artwork consists of three individual pieces. They are a play on perspective with one angle showing stylized cacti and another angle showing a family of quail.  Project is competed.
  • Fabrication has begun and is tentatively scheduled for installation by December 2025.
  • La Buena Vida Park was chosen in collaboration with Parks and Recreation for a new art piece.
  • Information gathering phase in progress to determine park public art project site.
  • City Council approved the concept design recommended by the City Art Board at the January 21, 2025 council meeting.
  • Contract is pending Legal acceptance of Artist requested revisions.

If/when appropriate, the City will host a Call for Artists. When available, the information can be found via this link. 

2018 General Obligation Bond Projects

Go Bond Project Updates

The City of Las Cruces has established an easy, online way for the public to check the status of the General Obligation (GO) Bond projects approved by voters. The GO Bond portal provides improved transparency and customer service to Las Crucens.

Below is the GO Bond portal. For additional information or to ask a question, please reach out to gobond@las-cruces.org.

GO Bond project schedules will be updated monthly. Due to the current market conditions with materials and labor force, schedules are subject to change.

About General Obligation Bonds

General Obligation (GO) Bonds are an important source of funding for basic capital improvements (bricks and mortar) that our growing community requires to thrive.

General Obligation Bonds are typically best suited for projects that benefit the general public but generate little or no revenue to pay debt service.

The City typically uses GO Bonds for initiatives including:

  • Parks and recreation facilities and improvements
  • Public facilities such as fire stations, police stations, libraries, senior centers
  • Infrastructure improvements such as roads, sidewalks, trails, and drainage facilities
  • Other projects with strong local support

Frequently Asked Questions

A General Obligation Bond is a form of debt financing secured by property tax revenues. General obligation bonds can be issued for general purpose projects. State Statute 3-30-5 outlines the authority to issue general obligation bonds and purpose.

City of Las Cruces current general obligation bond outstanding debt is $22,510,000.

State Constitution Article 9 Section 3 limits the amount of general obligation bonds issued by municipalities to 4% of total assessed valuation. The City of Las Cruces’ current general obligation bonding capacity is $82,681,309.

The City uses property tax revenues to pay for general obligation bonds. General obligation bond debt service is paid semi-annually (February and August). City’s outstanding general obligation bonds are on a twelve-year repayment schedule.

Debt service refers to the cash required to pay back interest and principal on debt obligations. The amount of debt service is one factor used to calculate the mill rate.

Bond cycling allows the city to issue new debt without increasing the debt service. The debt service stays leveled when debt is cycled. If general obligation bonds are structured to be cycled every four years, the debt service will decrease the fourth year but will level out with the new debt.

There will be a minimal decrease in property taxes if the bonds are not approved by voters. The tax rate will go down until the current general obligation bonds are paid off.

The GO bond questions on the ballot will not raise the City’s debt service level which is one factor in calculating property taxes. If the property’s assessed value increases, property taxes may go up.

Several factors determine how much you pay in property taxes. These include assessed value and location of the property. An increase in the assessed taxable value of the property will increase the property taxes. If governmental and/or educational entities increase their mill rate, property taxes will increase.

Taxable value on real and personal property is one-third of the total assessed value, minus any allowable exemptions. Net taxable value times the mill rate is total taxes owed.

For example:

Full Value of Property Total Assessed Value $150,000
Taxable Value Total Assessed Value ÷ 3 $50,000
Subtract Exemptions $0
Net Taxable Value $50,000
Calculate Total Taxes Owed Net Taxable Value * Mill Rate
$50,000 * 0.031258
$1562.90

Note:  The New Mexico Department of Finance and Administration may apply the yield control formula to limit the percentage by which total revenue generated by a property tax imposition may grow from year to year.

The assessed value is the dollar value assigned to a home or other piece of real estate for property tax purposes. The county assessor is responsible for valuing all real and personal property for taxing authorities in the county.

The mill rate is the amount of tax payable per dollar of the assessed value of a property. 1 mill is equal to $1 in property tax levied per $1,000 of the property’s assessed value. Different mill rates are charged by different agencies, including the city, the county, school boards, and the state. These are all combined to help calculate your final property tax bill. The current mill rate is 2.03. The mill rate will not increase with the GO bonds in the current ballot.

The New Mexico Department of Finance and Administration will determine the rate that each taxing entity will receive, also called Mill Rate. The portion of the taxes received by tax entities such as school districts and municipalities are based on their budgetary needs. Yield control rates place an additional limitation on property tax rates. Yield control rates limit the tax rate when property values are increased due to reassessment.

The mill rate established is applied to both existing and new property.

Send in your thoughts to gobond@las-cruces.org.

Many communities issue and repay GO Bonds on a regular cycle – e.g. every 2 to 6 years. The City will evaluate the need for GO Bond elections in the future.

Contact Us – Community Engagement Office

Email the Community Engagement Office: CLCengage@las-cruces.org

Physical Address: 700 N. Main Street, Las Cruces, NM 88001

Phone: (575) 541-2100

Register to Vote